Transportation Project

Local Agency Program Recovery (LAP-R) | General Rees Avenue Reconstruction and Resurfacing Project

This project entails reconstructing the roadway limits from Corrine Drive to Glenridge Way. The reconstruction includes installation of a stormwater drainage collection and conveyance system (pipes, curbs, inlets), narrower travel lanes, bicycle lanes, a new concrete sidewalk on the west side of the road, replacement of road base material and the use of a "green' asphalt removal and replacement process called Full Depth Reclamation. The length of the project is approximately 3,912 feet (0.741 miles) long.

Project Details
Project Contact Government Information
407-836-3111
* Project Funding Recap
Grant Amount for Project  $975,019.00
[+] Matching Funds $0.00
[+] External Funds $0.00
[=] Project Cost $975,019.00
Expenditures to Date  $306,926.84
Annual Expenditures
$306,926.84
*Project Cost is calculated through end of the previous business day. Expenditures to Date may not include all expended Matching Funds until after the end of the fiscal year. External funds do not flow through the Orange County financial system and are not represented in Expenditures to Date nor Annual Expenditures.
Federal Agency Dept. of Transportation
Grant Type Competitive
Passed through the State? Yes
Application Date 2/25/2009
BCC Approval Date 8/25/2009
Jobs Created / Retained Federal Job Creation Formula indicates 23 jobs will be created with this project.
Comments
Project Schedule: Anticipated FDOT NTP Date - 10/26/2009. Anticipated Advertisement Date - 10/27/2009. Anticipated Bid Opening Date (30 days advertised) - 11/30/2009. Anticipated Award Date - 3/1/2010. Anticipated contract execution - 3/30/2010. Anticipated Pre-Construction Meeting - 4/14/2010. Anticipated NTP to Contractor date - 4/21/2010. Construction days - 210. Anticipated Completion Date - 11/17/2010. Anticipated Final Acceptance Date - 1/16/2011.