Transportation Project

Local Agency Program Recovery (LAP-R) | Thorpe Road Bridge Replacement Project

The project consists of the removal of the existing bridge culvert, consisting of two 12-foot travel lanes, the construction of 2 new 10’x 6’ concrete box culverts to replace the existing Thorpe Road Bridge located between Bachman Road and Sidney Hayes Road. The net length of the project is 274 feet and includes the following the construction of storm water piping and associated structures, sidewalks, driveways, and handrail.

Project Details
Project Contact Government Information
407-836-3111
* Project Funding Recap
Grant Amount for Project  $412,423.00
[+] Matching Funds $0.00
[+] External Funds $0.00
[=] Project Cost $412,423.00
Expenditures to Date  $218,712.38
Annual Expenditures
$218,712.38
*Project Cost is calculated through end of the previous business day. Expenditures to Date may not include all expended Matching Funds until after the end of the fiscal year. External funds do not flow through the Orange County financial system and are not represented in Expenditures to Date nor Annual Expenditures.
Federal Agency Dept. of Transportation
Grant Type Competitive
Passed through the State? Yes
Application Date 2/25/2009
BCC Approval Date 8/25/2009
Jobs Created / Retained Federal Job Creation Formula indicates 12 jobs will be created with this project.
Comments
Project Schedule: Design Completion - Completed. Bid Package Submitted to FDOT - 10/16/2009. Anticipated FDOT NTP Date - 10/28/2009. Anticipated Advertisement Date - 11/17/2009. Anticipated Bid Opening Date (30 days advertised) - 12/10/2009. Anticipated Award Date - 03/16/2010. Anticipated Contract Execution - 04/15/2010. Anticipated Pre-Construction Meeting - 04/21/2010. Anticipated NTP to Contractor date - 04/26/2010. Construction day - 180. Anticipated Completion Date - 10/23/2010. Anticipated Final Acceptance Date - 12/22/2010.