Local Agency Program Recovery (LAP-R) | Taylor Creek Road Bridge Replacement Project

This project entails the replacement of the existing wooden bridge with a three-span structure utilizing precast, pre-stressed concrete beams with a cast-in-place deck. The substructure will consist of precast concrete pilings. The improvement will also include guardrail, retaining walls, drainage structures, concrete traffic railing barrier, driveways, sod and construction of a single travel lane in each direction. The project is 1,050 feet in length.

Project Details
Project Contact Government Information
407-836-3111
* Project Funding Recap
Grant Amount for Project  $2,750,000.00
[+] Matching Funds $0.00
[+] External Funds $0.00
[=] Project Cost $2,750,000.00
Expenditures to Date  $52,882.85
Annual Expenditures
$52,882.85
*Project Cost is calculated through end of the previous business day. Expenditures to Date may not include all expended Matching Funds until after the end of the fiscal year. External funds do not flow through the Orange County financial system and are not represented in Expenditures to Date nor Annual Expenditures.
Federal Agency Dept. of Transportation
Grant Type Competitive
Passed through the State? Yes
Application Date 2/25/2009
BCC Approval Date 8/25/2009
Jobs Created / Retained Federal Job Creation Formula indicates 37 jobs will be created with this project.
Comments
Project Schedule: Design Completion - Completed Bid Package Submitted to FDOT - 10/19/2009 Anticipated FDOT NTP Date - 11/02/2009 Anticipated Advertisement Date - 11/10/2009 Anticipated Bid Opening Date (30 days advertised) - 12/10/2009 Anticipated Award Date - 03/02/2010 Anticipated Contract Execution - 04/01/2010 Anticipated Pre-Construction Meeting - 04/06/2010 Anticipated NTP to Contractor date - 04/12/2010 Construction days - 270 Anticipated Completion Date - 01/07/2011 Anticipated Final Acceptance Date - 03/08/2011