Local Agency Program Recovery (LAP-R) | Dean Road Resurfacing Project

This project entails milling and resurfacing 2.5 inches of asphalt from all existing travel lanes from North of State Road 50 (Colonial Drive) to the south side of University Boulevard. Manhole and valve lids will be adjusted as necessary to match the new pavement. Sidewalk crossings at driveways and curb ramps will be reconstructed as necessary to meet ADA criteria. Roadside shoulders will be re-graded as necessary to meet vehicle drop-off criteria. The length of the project is approximately 9,842 feet (1.864 miles) long.

Project Details
Project Contact Government Information
407-836-3111
* Project Funding Recap
Grant Amount for Project  $1,186,807.00
[+] Matching Funds $0.00
[+] External Funds $0.00
[=] Project Cost $1,186,807.00
Expenditures to Date  $586,327.82
Annual Expenditures
$586,327.82
*Project Cost is calculated through end of the previous business day. Expenditures to Date may not include all expended Matching Funds until after the end of the fiscal year. External funds do not flow through the Orange County financial system and are not represented in Expenditures to Date nor Annual Expenditures.
Federal Agency Dept. of Transportation
Grant Type Competitive
Passed through the State? Yes
Application Date 2/25/2009
BCC Approval Date 8/25/2009
Jobs Created / Retained Federal Job Creation Formula indicates 37 jobs will be created with this project.
Comments
Project Schedule: Anticipated FDOT NTP Date - 10/26/2009. Anticipated Advertisement Date - 10/28/2009. Anticipated Bid Opening Date (30 days advertised) - 11/30/2009. Anticipated Award Date - 3/1/2010. Anticipated contract execution - 3/30/2010. Anticipated Pre-Construction Meeting - 4/14/2010. Anticipated NTP to Contractor date - 4/21/2010. Construction days - 150. Anticipated Completion Date - 9/18/2010. Anticipated Final Acceptance Date - 11/17/2010.